Production meeting - 12/12/16

Today we looked over our script.  We discussed what we should do. We also talked about what we should add in the script. We looked over the design and what would be going on. We then planned what our next move would be. I looked at the script and i gave my opinion on what i thought and what should be added and changed. We then selected our potential actors for our show. We placed our furniture in certain areas just as we planned out.

Script

 We finally came up with our script. We decided what is going to be said. We are still discussing the casting of the show.  I asked if we should have two commercials. As well as where they should be placed.




The script was created by Keeley Barnaby

Thursday, 8 December 2016

Lighting plans

Lighting plan                                           



*Black out *
Front lights fade in (5 AND 6) in and is on the host (use low key light)
Host introduces himself/herself …….

Host introduces the guest …….
After induction
light s 5 & 6 fade down
Lights 1&2 on when host introduces them
Then lights 3&4 on when guest introduces them

Host: both teams will be competing to see who has the better social thumb…………

* All studio lights turn on * (lights 1,2,3,4,,5 and 6)

Wednesday, 7 December 2016

Our discussion

Our group sat together and worked out what we should do and what we can work on.  We decided the structure of our show. Also what the challenges are going to be. 

Tuesday, 6 December 2016

Project journal - 06/12/16

Today as a group we went over our script and looked over our work. We made notes on our scripts and looked over what new ideas we can come up with. Many ideas that i came up with was:

  • To have a vote on twitter and have a graphic on screen.
  • I also had the idea of streaming from the iPad's on to a screen. The app i wanted to use was 'Shou mobile game streaming' however i realised that app was for gaming that  recording whats going on the iPad.
  • While we were discussing our time management i came up with the idea of having commercials.
  • I also thought that we should have the commercials before the results are given. This could cause audience members to carry on watching the show.
  • We decided that we would use the muisc.ly app on the third round of the game.
  • We are still debating on the use of prerecorded videos.
  • We talked about a game point structure.


Monday, 5 December 2016

Budget

For our project Brefin decided to finish our budget.

Expenses & Jobs roles Amount of No. Price of EachTotal
Rent studio 1£40 Per Hour (10hr) £400
Equipments E.g Cameras, 5 ipads £379£1,895
Food 0£0£0
Travel 0£0£0
Costumes/ Materials 0£0£0
Producers 1£195 (Per Hr) 1,950
Director 2£155 (Per Hr)£1,550
Cast7£15 (Per Hr) £1,050
Production Staff9£25 (Per Hr)£2,250
Camera Operator3£45 (Per Hr)£1,350
Lighting Techician 1£25 (Per Hr)£250
Production Manager1£35 (Per Hr)£350
Script Supervisor2£65 (Per Hr)£1,300
Costume Design1£24 (Per Hr)£240
Hair/Make up 1£24 (Per Hr)£240
Editor4£65 (Per Hr)£2,600
Sound Operator 1£35 (Per Hr)£350
Floor Manger 1£25 (Per Hr)£250
£16,025
Budget = £20,000

Friday, 2 December 2016

Shot list

This is the first page of the shot list that i have made. I Was unable to make the rest because of delays and i was not able to get hold of the final script. 


Floor planning

This is the floorplanning plan for our show. Which i made while doing work in the studio.